The largest domestic lithium-ion energy storage station built by the Ningde era started with a grid-connected capacity of 108MWh and a service life of 20 years

On January 14, 2020, the largest domestic grid-side station-type lithium-ion battery energy storage power station in Fujian—the first phase (30MW / 108MWh) of the Jinjiang Energy Storage Pilot Project in Fujian was launched and connected to the grid. At 9:24 on January 15, The grid connection was successful once.

Ningde Times is responsible for the system integration of the entire energy storage system (battery system + PCS + EMS). The cycle life of the battery cell can reach 12,000 times. Charge and discharge 1.5-2.0 times per day according to local dispatching instructions. The service life is expected to exceed 20 years. 108MWh is equivalent to 108,000 kilowatt-hours of electricity. According to estimates, the energy storage power station can be fully discharged once to guarantee the daily power consumption of more than 13 thousand families of three.